The Victoria

Phase 1 & 2

Project Title: The Victoria (Phase 1 & 2)

Client: Sanctuary Homes

Main Contractor: Cruden

Location: Glasgow

Contract Duration: 100 weeks

Completed: 2023

Brief Overview of Project:

Forming part of the mixed-use redevelopment of the old Victoria Infirmary site in Glasgow’s Battlefield district, Lesterose Scotland delivered masonry façade elements to 9 newly constructed accommodation blocks.

Challenges:

The main challenge overcome on this project was programme constraints associated with the simultaneous delivery of multiple residential blocks. This was well managed by the Lesterose Scotland project team through diligent resource management and regular programme review discussions with the main contractor.